Mumbai–Amdavad Bullet Train Project Update
Published March 12, 2026
Views 204K | Likes 3.57K | Comments 645
At a glance
Views
204,239
Likes
3,575
Comments
645
Performance vs. channel
Outlier score
Engagement rate
More features coming
We're working on new analytics and tools. Stay tuned.
About
Mumbai–Amdavad Bullet Train Project Update (As on 8th March 2026) The project is being implemented with world-class technology. 🏗️ Progress Updates So Far * 339 km of viaduct completed. * 428 km of pier work completed. * 6,500+ OHE masts installed, covering approx. 151 route km of the mainline viaduct. * 5 lakh+ noi…